MAT-2026-034 · Engr. Carlos M. Reyes · Sep 6, 2026

CancelledNot AssessedRoutine
Physical progress89%
Financial progress88%
Scheduled dateSep 6, 2026Pending completion
Findings00 site photos

Inspection Information

Inspection code
INS-2026-055
Inspection type
Routine
Status
Cancelled
Scheduled date
Sep 6, 2026
Completed date
Not yet completed
Overall rating
Not Assessed
Remarks
Inspection postponed due to inclement weather.

Project Information

Project code
MAT-2026-034
Project title
Evacuation Center Improvement – Sulangan
Project type
Disaster resilience
Barangay
Sulangan
Contractor
Pacificline General Services

Inspector Details

Inspector
Engr. Carlos M. Reyes
Designation
Municipal Engineer

Progress at Inspection

Physical progress
89%
Financial progress
88%