Track every project through the pipeline — from proposal to completion.

Total projects96FY 2026 portfolio
Total budget₱472.7Mcombined allocation
Funded32approved for execution
In implementation21active construction
Completed0finished projects
At risk41high or critical risk

Pipeline status

Draft
11 (11%)
Submitted
11 (11%)
Under Review
11 (11%)
Prioritized
11 (11%)
Funded
32 (33%)
Deferred
10 (10%)
Rejected
10 (10%)

Delivery stage

Planning
21 (22%)
Readiness
11 (11%)
Procurement
11 (11%)
Implementation
21 (22%)
Inspection
10 (10%)
Closeout
11 (11%)
On Hold
11 (11%)

Risk distribution

Low
44 (46%)
Moderate
11 (11%)
High
23 (24%)
Critical
18 (19%)

All projects

Complete project roster with current pipeline status, delivery stage, progress, and risk level.

96 projects
Level III Water System Expansion – SisigonMunicipal Engineering OfficeMAT-2026-017SisigonWater supplyDeferredInspection
93%
99%
₱2.4MLow—
Digital Permit and Tracking Kiosk – TugasMunicipal IT OfficeMAT-2026-040TugasDigital servicePrioritizedCloseout
92%
97%
₱3.5MHigh12d
Evacuation Center Improvement – SulanganMunicipal DRRM OfficeMAT-2026-034SulanganDisaster resilienceFundedImplementation
89%
88%
₱5.5MLow—
Fishport Rehabilitation – BalocaweMunicipal Agriculture OfficeMAT-2026-057BalocaweFisheryUnder ReviewImplementation
88%
86%
₱7.4MLow—
Coastal Protection and Seawall – Bon-Ot BigMunicipal Engineering OfficeMAT-2026-080Bon-Ot BigCoastal protectionDeferredInspection
87%
84%
₱7.3MHigh12d
Drainage Canal Improvement – Santa IsabelMunicipal Engineering OfficeMAT-2026-022Santa IsabelDrainagePrioritizedCloseout
83%
88%
₱2.7MLow—
Farm-to-Market Road Concreting – Municipality-wideMunicipal Engineering OfficeMAT-2026-016MunicipalRoad and transportFundedImplementation
80%
79%
₱14.6MModerate—
Barangay Multi-Purpose Hall – SinalmacanMunicipal Engineering OfficeMAT-2026-039SinalmacanPublic buildingUnder ReviewImplementation
79%
77%
₱1.8MCritical74d
Level III Water System Expansion – SulanganMunicipal Engineering OfficeMAT-2026-062SulanganWater supplyDeferredInspection
78%
75%
₱6.1MLow—
Digital Permit and Tracking Kiosk – BanogaoMunicipal IT OfficeMAT-2026-085BanogaoDigital servicePrioritizedCloseout
77%
73%
₱1.8MHigh12d
Evacuation Center Improvement – MambajogMunicipal DRRM OfficeMAT-2026-004MambajogDisaster resiliencePrioritizedCloseout
74%
79%
₱5.7MLow—
Evacuation Center Improvement – TabunanMunicipal DRRM OfficeMAT-2026-079TabunanDisaster resilienceFundedImplementation
74%
82%
₱6.5MLow—
School Classroom Repair – ManjunladLocal School BoardMAT-2026-021ManjunladEducation facilityUnder ReviewImplementation
70%
68%
₱2MHigh34d
Footbridge Construction – PawaMunicipal Engineering OfficeMAT-2026-044PawaRoad and transportDeferredInspection
69%
66%
₱5.8MLow—
Drainage Canal Improvement – Sinang-AtanMunicipal Engineering OfficeMAT-2026-067Sinang-AtanDrainagePrioritizedCloseout
68%
64%
₱3.6MLow—
Farm-to-Market Road Concreting – Municipality-wideMunicipal Engineering OfficeMAT-2026-061MunicipalRoad and transportFundedImplementation
65%
73%
₱16MLow—
Barangay Multi-Purpose Hall – SinibaranMunicipal Engineering OfficeMAT-2026-084SinibaranPublic buildingUnder ReviewImplementation
64%
71%
₱2.8MHigh34d
Rural Health Station Rehabilitation – Coron-coronMunicipal Health OfficeMAT-2026-003Coron-coronHealth facilityUnder ReviewImplementation
61%
59%
₱3.3MLow—
Solar Streetlight Installation – HidhidMunicipal Engineering OfficeMAT-2026-026HidhidElectrificationDeferredInspection
60%
57%
₱3.5MCritical74d
Evacuation Center Improvement – ManurabiMunicipal DRRM OfficeMAT-2026-049ManurabiDisaster resiliencePrioritizedCloseout
59%
55%
₱8.3MHigh34d
1–20 of 96