Appropriation₱346.9M108 allocation records
Financial reports
Fund Utilization
Understand how appropriations move into obligations and actual project payments.
Obligations₱137.2M40% of appropriation
Disbursements₱100.6M29% paid
Available balance₱209.7MUnobligated funds
Obligation rate40%Healthy execution
Disbursement rate29%Needs attention
Budget execution overview
How approved funding moves into obligations and actual payments.
Appropriation₱346.9M
Obligations₱137.2M
Disbursements₱100.6M
40% obligated29% disbursed
Utilization by fund source
Largest funding sources ranked by current appropriation.
Provincial Assistance₱63.9M
37% obligated27% paid
Municipal General Fund₱54.9M
41% obligated30% paid
Special Education Fund₱45.9M
32% obligated23% paid
Barangay Development Fund₱45.9M
48% obligated35% paid
Local Disaster Risk Reduction and Management Fund₱44.9M
42% obligated33% paid
20% Municipal Development Fund₱44.4M
40% obligated30% paid
National Government Grant₱42.9M
39% obligated29% paid
Obligations Disbursements
Utilization by barangay
Municipal and barangay execution at a glance.
Municipality-wide₱44.3M
65% obligated45% paid
Mambajog₱20.7M
23% obligated14% paid
Bariis₱16.2M
37% obligated33% paid
Bon-Ot Small₱14.9M
25% obligated18% paid
Santa Isabel₱13.2M
20% obligated16% paid
Sulangan₱13.1M
71% obligated57% paid
Bon-Ot Big₱12.2M
59% obligated37% paid
Obligations Disbursements
Monthly disbursement trend
Cumulative FY 2026 payment movement across the filtered portfolio.
JanFebMarAprMayJunJulAugSepOctNovDec
Needs attention
Projects with delayed execution or financial balances requiring follow-up.
Drainage Canal Improvement – BariisMAT-2026-007 · 34 days behind schedule
ReviewDay Care Center Construction – Bon-Ot SmallMAT-2026-013 · 74 days behind schedule
ReviewFootbridge Construction – CamcamanMAT-2026-014 · 34 days behind schedule
ReviewSchool Classroom Repair – ManjunladMAT-2026-021 · 34 days behind schedule
ReviewSolar Streetlight Installation – HidhidMAT-2026-026 · 74 days behind schedule
ReviewDay Care Center Construction – SinibaranMAT-2026-028 · 34 days behind schedule
ReviewProject utilization detail
Audit-level allocation rows behind the graphical report.
Rows per page1–15 of 108Page 1 of 8