Coastal Protection and Seawall – Bariis

INS-2026-059· Bariis·Milestone Inspection

INS-2026-059 — Milestone Inspection

MAT-2026-035 · LGOO Ana P. Santos · Sep 10, 2026

CompletedUnsatisfactoryMilestone
Physical progress17%
Financial progress22%
Scheduled dateSep 10, 2026Completed Sep 12, 2026
Findings49 site photos

Inspection Information

Inspection code
INS-2026-059
Inspection type
Milestone
Status
Completed
Scheduled date
Sep 10, 2026
Completed date
Sep 12, 2026
Overall rating
Unsatisfactory
Remarks
Inspection completed as scheduled. All items documented.

Project Information

Project code
MAT-2026-035
Project title
Coastal Protection and Seawall – Bariis
Project type
Coastal protection
Barangay
Bariis
Contractor
Bicol Prime Builders

Inspector Details

Inspector
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress at Inspection

Physical progress
17%
Financial progress
22%
17%