Solar Streetlight Installation – Sinibaran

INS-2026-091· Sinibaran·Routine Inspection

INS-2026-091 — Routine Inspection

MAT-2026-056 · Engr. Maria D. Santos · Sep 17, 2026

ScheduledNot AssessedRoutine
Physical progress8%
Financial progress17%
Scheduled dateSep 17, 2026Pending completion
Findings00 site photos

Inspection Information

Inspection code
INS-2026-091
Inspection type
Routine
Status
Scheduled
Scheduled date
Sep 17, 2026
Completed date
Not yet completed
Overall rating
Not Assessed
Remarks
Inspection scheduled per approved monitoring plan.

Project Information

Project code
MAT-2026-056
Project title
Solar Streetlight Installation – Sinibaran
Project type
Electrification
Barangay
Sinibaran
Contractor
Not assigned

Inspector Details

Inspector
Engr. Maria D. Santos
Designation
Assistant Municipal Engineer

Progress at Inspection

Physical progress
8%
Financial progress
17%
8%