Project workspace

Project Workspace

Livelihood Processing Center – Coron-coron

INS-2026-163· Coron-coron·Routine Inspection

INS-2026-163 — Routine Inspection

MAT-2025-098 · Engr. Rafael T. Dizon · Sep 14, 2026

CompletedNeeds ImprovementRoutine
Physical progress100%
Financial progress94%
Scheduled dateSep 14, 2026Completed Sep 16, 2026
Findings35 site photos

Inspection Information

Inspection code
INS-2026-163
Inspection type
Routine
Status
Completed
Scheduled date
Sep 14, 2026
Completed date
Sep 16, 2026
Overall rating
Needs Improvement
Remarks
Inspection completed as scheduled. All items documented.

Project Information

Project code
MAT-2025-098
Project title
Livelihood Processing Center – Coron-coron
Project type
Livelihood
Barangay
Coron-coron
Contractor
Matnog Builders Cooperative

Inspector Details

Inspector
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress at Inspection

Physical progress
100%
Financial progress
94%
100%