Level III Water System Expansion – Tabunan
INS-2026-179· Tabunan·Milestone Inspection
INS-2026-179 — Milestone Inspection
MAT-2025-107 · LGOO Ana P. Santos · Sep 5, 2026
CompletedUnsatisfactoryMilestone
Inspection Information
- Inspection code
- INS-2026-179
- Inspection type
- Milestone
- Status
- Completed
- Scheduled date
- Sep 5, 2026
- Completed date
- Sep 7, 2026
- Overall rating
- Unsatisfactory
- Remarks
- Inspection completed as scheduled. All items documented.
Project Information
- Project code
- MAT-2025-107
- Project title
- Level III Water System Expansion – Tabunan
- Project type
- Water supply
- Barangay
- Tabunan
- Contractor
- South Luzon Infrastructure Corp.
Inspector Details
- Inspector
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress at Inspection
- Physical progress
- 55%
- Financial progress
- 60%
55%