Communal Irrigation System – Calpi
INS-2026-199· Calpi·Routine Inspection
INS-2026-199 — Routine Inspection
MAT-2025-120 · LGOO Ana P. Santos · Sep 25, 2026
CompletedUnsatisfactoryRoutine
Inspection Information
- Inspection code
- INS-2026-199
- Inspection type
- Routine
- Status
- Completed
- Scheduled date
- Sep 25, 2026
- Completed date
- Sep 27, 2026
- Overall rating
- Unsatisfactory
- Remarks
- Inspection completed as scheduled. All items documented.
Project Information
- Project code
- MAT-2025-120
- Project title
- Communal Irrigation System – Calpi
- Project type
- Irrigation
- Barangay
- Calpi
- Contractor
- Bicol Prime Builders
Inspector Details
- Inspector
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress at Inspection
- Physical progress
- 84%
- Financial progress
- 92%
84%