PRG-2026-008 — Monthly Progress Report

MAT-2026-004 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

VerifiedMonthly
Physical progress74%
Financial progress79%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+37% physical this period

Report Information

Report code
PRG-2026-008
Report type
Monthly
Status
Verified
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2026-004
Project title
Evacuation Center Improvement – Mambajog
Project type
Disaster resilience
Barangay
Mambajog
Contractor
Pacificline General Services

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
37% → 74% (+37%)
Financial progress
39% → 79% (+40%)
Slippage
On track
74%

Issues & Next Steps

Issues & concerns
Intermittent rainfall caused 2-day work stoppage. Contractor adjusted schedule accordingly.
Next steps
Continue with structural framing and begin wall construction in the next period.