Evacuation Center Improvement – Mambajog
PRG-2026-008· Mambajog·Monthly Report
PRG-2026-008 — Monthly Progress Report
MAT-2026-004 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
VerifiedMonthly
Report Information
- Report code
- PRG-2026-008
- Report type
- Monthly
- Status
- Verified
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2026-004
- Project title
- Evacuation Center Improvement – Mambajog
- Project type
- Disaster resilience
- Barangay
- Mambajog
- Contractor
- Pacificline General Services
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 37% → 74% (+37%)
- Financial progress
- 39% → 79% (+40%)
- Slippage
- On track
74%
Issues & Next Steps
- Issues & concerns
- Intermittent rainfall caused 2-day work stoppage. Contractor adjusted schedule accordingly.
- Next steps
- Continue with structural framing and begin wall construction in the next period.