Day Care Center Construction – Bon-Ot Small

PRG-2026-023· Bon-Ot Small·Monthly Report

PRG-2026-023 — Monthly Progress Report

MAT-2026-013 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

VerifiedMonthly74d behind
Physical progress41%
Financial progress37%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+21% physical this period

Report Information

Report code
PRG-2026-023
Report type
Monthly
Status
Verified
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2026-013
Project title
Day Care Center Construction – Bon-Ot Small
Project type
Social welfare
Barangay
Bon-Ot Small
Contractor
Matnog Builders Cooperative

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
20% → 41% (+21%)
Financial progress
18% → 37% (+19%)
Slippage
74 days behind schedule
41%

Issues & Next Steps

Issues & concerns
Material cost variance of 3.2% noted. Within allowable budget contingency.
Next steps
Coordinate with DPWH for road tie-in at intersection point.