Level III Water System Expansion – Sisigon

PRG-2026-029· Sisigon·Monthly Report

PRG-2026-029 — Monthly Progress Report

MAT-2026-017 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

VerifiedMonthly
Physical progress93%
Financial progress99%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+47% physical this period

Report Information

Report code
PRG-2026-029
Report type
Monthly
Status
Verified
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2026-017
Project title
Level III Water System Expansion – Sisigon
Project type
Water supply
Barangay
Sisigon
Contractor
South Luzon Infrastructure Corp.

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
46% → 93% (+47%)
Financial progress
49% → 99% (+50%)
Slippage
On track
93%

Issues & Next Steps

Issues & concerns
No significant issues encountered during reporting period. Work proceeding as planned.
Next steps
Prepare for pre-final inspection. Complete punch list items.