Project workspace

Project Workspace

Drainage Canal Improvement – Santa Isabel

PRG-2026-038· Santa Isabel·Monthly Report

PRG-2026-038 — Monthly Progress Report

MAT-2026-022 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

SubmittedMonthly
Physical progress83%
Financial progress88%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+42% physical this period

Report Information

Report code
PRG-2026-038
Report type
Monthly
Status
Submitted
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2026-022
Project title
Drainage Canal Improvement – Santa Isabel
Project type
Drainage
Barangay
Santa Isabel
Contractor
South Luzon Infrastructure Corp.

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
41% → 83% (+42%)
Financial progress
44% → 88% (+44%)
Slippage
On track
83%

Issues & Next Steps

Issues & concerns
Right-of-way concern raised by adjacent property owner. Coordinating with barangay officials.
Next steps
Mobilize additional crew to recover 2-day slippage from weather delay.