Solar Streetlight Installation – Hidhid

PRG-2026-044· Hidhid·Monthly Report

PRG-2026-044 — Monthly Progress Report

MAT-2026-026 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

VerifiedMonthly74d behind
Physical progress60%
Financial progress57%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+30% physical this period

Report Information

Report code
PRG-2026-044
Report type
Monthly
Status
Verified
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2026-026
Project title
Solar Streetlight Installation – Hidhid
Project type
Electrification
Barangay
Hidhid
Contractor
Mayon Construction Services

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
30% → 60% (+30%)
Financial progress
28% → 57% (+29%)
Slippage
74 days behind schedule
60%

Issues & Next Steps

Issues & concerns
Concrete testing results within specification. Compression strength at 28 days: 4,200 PSI.
Next steps
Install drainage outfall and connect to existing municipal system.