Coastal Protection and Seawall – Bariis
PRG-2026-059· Bariis·Monthly Report
PRG-2026-059 — Monthly Progress Report
MAT-2026-035 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
SubmittedMonthly34d behind
Report Information
- Report code
- PRG-2026-059
- Report type
- Monthly
- Status
- Submitted
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-035
- Project title
- Coastal Protection and Seawall – Bariis
- Project type
- Coastal protection
- Barangay
- Bariis
- Contractor
- Bicol Prime Builders
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 13% → 27% (+14%)
- Financial progress
- 16% → 33% (+17%)
- Slippage
- 34 days behind schedule
27%
Issues & Next Steps
- Issues & concerns
- Workforce reduced to 60% due to local fiesta. Full crew expected next reporting period.
- Next steps
- Conduct concrete strength test and proceed with second floor slab if passed.