Project workspace

Project Workspace

Coastal Protection and Seawall – Bariis

PRG-2026-059· Bariis·Monthly Report

PRG-2026-059 — Monthly Progress Report

MAT-2026-035 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

SubmittedMonthly34d behind
Physical progress27%
Financial progress33%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+14% physical this period

Report Information

Report code
PRG-2026-059
Report type
Monthly
Status
Submitted
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2026-035
Project title
Coastal Protection and Seawall – Bariis
Project type
Coastal protection
Barangay
Bariis
Contractor
Bicol Prime Builders

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
13% → 27% (+14%)
Financial progress
16% → 33% (+17%)
Slippage
34 days behind schedule
27%

Issues & Next Steps

Issues & concerns
Workforce reduced to 60% due to local fiesta. Full crew expected next reporting period.
Next steps
Conduct concrete strength test and proceed with second floor slab if passed.