PRG-2026-068· Tugas·Monthly Report

PRG-2026-068 — Monthly Progress Report

MAT-2026-040 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

ReturnedMonthly12d behind
Physical progress92%
Financial progress97%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+46% physical this period

Report Information

Report code
PRG-2026-068
Report type
Monthly
Status
Returned
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2026-040
Project title
Digital Permit and Tracking Kiosk – Tugas
Project type
Digital service
Barangay
Tugas
Contractor
Bicol Prime Builders

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
46% → 92% (+46%)
Financial progress
48% → 97% (+49%)
Slippage
12 days behind schedule
92%

Issues & Next Steps

Issues & concerns
Concrete testing results within specification. Compression strength at 28 days: 4,200 PSI.
Next steps
Install drainage outfall and connect to existing municipal system.