PRG-2026-068· Tugas·Monthly Report
PRG-2026-068 — Monthly Progress Report
MAT-2026-040 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
ReturnedMonthly12d behind
Report Information
- Report code
- PRG-2026-068
- Report type
- Monthly
- Status
- Returned
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2026-040
- Project title
- Digital Permit and Tracking Kiosk – Tugas
- Project type
- Digital service
- Barangay
- Tugas
- Contractor
- Bicol Prime Builders
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 46% → 92% (+46%)
- Financial progress
- 48% → 97% (+49%)
- Slippage
- 12 days behind schedule
92%
Issues & Next Steps
- Issues & concerns
- Concrete testing results within specification. Compression strength at 28 days: 4,200 PSI.
- Next steps
- Install drainage outfall and connect to existing municipal system.