Footbridge Construction – Pawa
PRG-2026-074· Pawa·Monthly Report
PRG-2026-074 — Monthly Progress Report
MAT-2026-044 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
DraftMonthly
Report Information
- Report code
- PRG-2026-074
- Report type
- Monthly
- Status
- Draft
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- —
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-044
- Project title
- Footbridge Construction – Pawa
- Project type
- Road and transport
- Barangay
- Pawa
- Contractor
- Pacificline General Services
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 34% → 69% (+35%)
- Financial progress
- 33% → 66% (+33%)
- Slippage
- On track
69%
Issues & Next Steps
- Issues & concerns
- Minor discrepancy in elevation readings resolved on-site with the project engineer.
- Next steps
- Begin roofing installation upon delivery of pre-fabricated trusses.