Footbridge Construction – Pawa

PRG-2026-074· Pawa·Monthly Report

PRG-2026-074 — Monthly Progress Report

MAT-2026-044 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

DraftMonthly
Physical progress69%
Financial progress66%
Reporting periodAug 15 – Aug 28, 2026Not yet submitted
Work items4+35% physical this period

Report Information

Report code
PRG-2026-074
Report type
Monthly
Status
Draft
Period
Aug 15 – Aug 28, 2026
Submitted date
—
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2026-044
Project title
Footbridge Construction – Pawa
Project type
Road and transport
Barangay
Pawa
Contractor
Pacificline General Services

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
34% → 69% (+35%)
Financial progress
33% → 66% (+33%)
Slippage
On track
69%

Issues & Next Steps

Issues & concerns
Minor discrepancy in elevation readings resolved on-site with the project engineer.
Next steps
Begin roofing installation upon delivery of pre-fabricated trusses.