Evacuation Center Improvement – Manurabi
PRG-2026-083· Manurabi·Monthly Report
PRG-2026-083 — Monthly Progress Report
MAT-2026-049 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
ArchivedMonthly34d behind
Report Information
- Report code
- PRG-2026-083
- Report type
- Monthly
- Status
- Archived
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2026-049
- Project title
- Evacuation Center Improvement – Manurabi
- Project type
- Disaster resilience
- Barangay
- Manurabi
- Contractor
- Pacificline General Services
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 29% → 59% (+30%)
- Financial progress
- 27% → 55% (+28%)
- Slippage
- 34 days behind schedule
59%
Issues & Next Steps
- Issues & concerns
- Workforce reduced to 60% due to local fiesta. Full crew expected next reporting period.
- Next steps
- Conduct concrete strength test and proceed with second floor slab if passed.