Livelihood Processing Center – Camachiles
PRG-2026-089· Camachiles·Monthly Report
PRG-2026-089 — Monthly Progress Report
MAT-2026-053 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
ReturnedMonthly
Report Information
- Report code
- PRG-2026-089
- Report type
- Monthly
- Status
- Returned
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-053
- Project title
- Livelihood Processing Center – Camachiles
- Project type
- Livelihood
- Barangay
- Camachiles
- Contractor
- Matnog Builders Cooperative
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 18% → 36% (+18%)
- Financial progress
- 21% → 42% (+21%)
- Slippage
- On track
36%
Issues & Next Steps
- Issues & concerns
- Delivery of steel reinforcement bars delayed by 3 days from supplier. No critical impact on overall timeline.
- Next steps
- Complete remaining earthworks and proceed to sub-base preparation.