Day Care Center Construction – Calayuan
PRG-2026-098· Calayuan·Monthly Report
PRG-2026-098 — Monthly Progress Report
MAT-2026-058 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
SubmittedMonthly
Report Information
- Report code
- PRG-2026-098
- Report type
- Monthly
- Status
- Submitted
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2026-058
- Project title
- Day Care Center Construction – Calayuan
- Project type
- Social welfare
- Barangay
- Calayuan
- Contractor
- Matnog Builders Cooperative
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 13% → 26% (+13%)
- Financial progress
- 15% → 31% (+16%)
- Slippage
- On track
26%
Issues & Next Steps
- Issues & concerns
- Minor discrepancy in elevation readings resolved on-site with the project engineer.
- Next steps
- Begin roofing installation upon delivery of pre-fabricated trusses.