Level III Water System Expansion – Sulangan
PRG-2026-104· Sulangan·Monthly Report
PRG-2026-104 — Monthly Progress Report
MAT-2026-062 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
ArchivedMonthly
Report Information
- Report code
- PRG-2026-104
- Report type
- Monthly
- Status
- Archived
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-062
- Project title
- Level III Water System Expansion – Sulangan
- Project type
- Water supply
- Barangay
- Sulangan
- Contractor
- South Luzon Infrastructure Corp.
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 39% → 78% (+39%)
- Financial progress
- 37% → 75% (+38%)
- Slippage
- On track
78%
Issues & Next Steps
- Issues & concerns
- Intermittent rainfall caused 2-day work stoppage. Contractor adjusted schedule accordingly.
- Next steps
- Continue with structural framing and begin wall construction in the next period.