Solar Streetlight Installation – Lajong
PRG-2026-119· Lajong·Monthly Report
PRG-2026-119 — Monthly Progress Report
MAT-2026-071 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
SubmittedMonthly
Report Information
- Report code
- PRG-2026-119
- Report type
- Monthly
- Status
- Submitted
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-071
- Project title
- Solar Streetlight Installation – Lajong
- Project type
- Electrification
- Barangay
- Lajong
- Contractor
- Mayon Construction Services
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 22% → 45% (+23%)
- Financial progress
- 25% → 51% (+26%)
- Slippage
- On track
45%
Issues & Next Steps
- Issues & concerns
- Material cost variance of 3.2% noted. Within allowable budget contingency.
- Next steps
- Coordinate with DPWH for road tie-in at intersection point.