PRG-2026-119· Lajong·Monthly Report

PRG-2026-119 — Monthly Progress Report

MAT-2026-071 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

SubmittedMonthly
Physical progress45%
Financial progress51%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+23% physical this period

Report Information

Report code
PRG-2026-119
Report type
Monthly
Status
Submitted
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2026-071
Project title
Solar Streetlight Installation – Lajong
Project type
Electrification
Barangay
Lajong
Contractor
Mayon Construction Services

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
22% → 45% (+23%)
Financial progress
25% → 51% (+26%)
Slippage
On track
45%

Issues & Next Steps

Issues & concerns
Material cost variance of 3.2% noted. Within allowable budget contingency.
Next steps
Coordinate with DPWH for road tie-in at intersection point.