Farm-to-Market Road Concreting – Municipality-wide

PRG-2026-128· Municipality-wide·Monthly Report

PRG-2026-128 — Monthly Progress Report

MAT-2026-076 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

VerifiedMonthly
Physical progress35%
Financial progress40%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+18% physical this period

Report Information

Report code
PRG-2026-128
Report type
Monthly
Status
Verified
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2026-076
Project title
Farm-to-Market Road Concreting – Municipality-wide
Project type
Road and transport
Barangay
Municipality-wide
Contractor
Mayon Construction Services

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
17% → 35% (+18%)
Financial progress
20% → 40% (+20%)
Slippage
On track
35%

Issues & Next Steps

Issues & concerns
Intermittent rainfall caused 2-day work stoppage. Contractor adjusted schedule accordingly.
Next steps
Continue with structural framing and begin wall construction in the next period.