Coastal Protection and Seawall – Bon-Ot Big

PRG-2026-134· Bon-Ot Big·Monthly Report

PRG-2026-134 — Monthly Progress Report

MAT-2026-080 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

VerifiedMonthly12d behind
Physical progress87%
Financial progress84%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+44% physical this period

Report Information

Report code
PRG-2026-134
Report type
Monthly
Status
Verified
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2026-080
Project title
Coastal Protection and Seawall – Bon-Ot Big
Project type
Coastal protection
Barangay
Bon-Ot Big
Contractor
Bicol Prime Builders

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
43% → 87% (+44%)
Financial progress
42% → 84% (+42%)
Slippage
12 days behind schedule
87%

Issues & Next Steps

Issues & concerns
Right-of-way concern raised by adjacent property owner. Coordinating with barangay officials.
Next steps
Mobilize additional crew to recover 2-day slippage from weather delay.