PRG-2026-134· Bon-Ot Big·Monthly Report
PRG-2026-134 — Monthly Progress Report
MAT-2026-080 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
VerifiedMonthly12d behind
Report Information
- Report code
- PRG-2026-134
- Report type
- Monthly
- Status
- Verified
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-080
- Project title
- Coastal Protection and Seawall – Bon-Ot Big
- Project type
- Coastal protection
- Barangay
- Bon-Ot Big
- Contractor
- Bicol Prime Builders
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 43% → 87% (+44%)
- Financial progress
- 42% → 84% (+42%)
- Slippage
- 12 days behind schedule
87%
Issues & Next Steps
- Issues & concerns
- Right-of-way concern raised by adjacent property owner. Coordinating with barangay officials.
- Next steps
- Mobilize additional crew to recover 2-day slippage from weather delay.