Digital Permit and Tracking Kiosk – Banogao
PRG-2026-143· Banogao·Monthly Report
PRG-2026-143 — Monthly Progress Report
MAT-2026-085 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
SubmittedMonthly12d behind
Report Information
- Report code
- PRG-2026-143
- Report type
- Monthly
- Status
- Submitted
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2026-085
- Project title
- Digital Permit and Tracking Kiosk – Banogao
- Project type
- Digital service
- Barangay
- Banogao
- Contractor
- Bicol Prime Builders
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 38% → 77% (+39%)
- Financial progress
- 36% → 73% (+37%)
- Slippage
- 12 days behind schedule
77%
Issues & Next Steps
- Issues & concerns
- Material cost variance of 3.2% noted. Within allowable budget contingency.
- Next steps
- Coordinate with DPWH for road tie-in at intersection point.