Footbridge Construction – Poropandan
PRG-2026-149· Poropandan·Monthly Report
PRG-2026-149 — Monthly Progress Report
MAT-2026-089 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
VerifiedMonthly
Report Information
- Report code
- PRG-2026-149
- Report type
- Monthly
- Status
- Verified
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2026-089
- Project title
- Footbridge Construction – Poropandan
- Project type
- Road and transport
- Barangay
- Poropandan
- Contractor
- Pacificline General Services
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 27% → 54% (+27%)
- Financial progress
- 30% → 60% (+30%)
- Slippage
- On track
54%
Issues & Next Steps
- Issues & concerns
- No significant issues encountered during reporting period. Work proceeding as planned.
- Next steps
- Prepare for pre-final inspection. Complete punch list items.