Evacuation Center Improvement – Paghuliran
PRG-2026-158· Paghuliran·Monthly Report
PRG-2026-158 — Monthly Progress Report
MAT-2026-094 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
DraftMonthly
Report Information
- Report code
- PRG-2026-158
- Report type
- Monthly
- Status
- Draft
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- —
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2026-094
- Project title
- Evacuation Center Improvement – Paghuliran
- Project type
- Disaster resilience
- Barangay
- Paghuliran
- Contractor
- Pacificline General Services
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 22% → 44% (+22%)
- Financial progress
- 24% → 49% (+25%)
- Slippage
- On track
44%
Issues & Next Steps
- Issues & concerns
- Right-of-way concern raised by adjacent property owner. Coordinating with barangay officials.
- Next steps
- Mobilize additional crew to recover 2-day slippage from weather delay.