Evacuation Center Improvement – Paghuliran

PRG-2026-158· Paghuliran·Monthly Report

PRG-2026-158 — Monthly Progress Report

MAT-2026-094 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

DraftMonthly
Physical progress44%
Financial progress49%
Reporting periodAug 15 – Aug 28, 2026Not yet submitted
Work items4+22% physical this period

Report Information

Report code
PRG-2026-158
Report type
Monthly
Status
Draft
Period
Aug 15 – Aug 28, 2026
Submitted date
—
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2026-094
Project title
Evacuation Center Improvement – Paghuliran
Project type
Disaster resilience
Barangay
Paghuliran
Contractor
Pacificline General Services

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
22% → 44% (+22%)
Financial progress
24% → 49% (+25%)
Slippage
On track
44%

Issues & Next Steps

Issues & concerns
Right-of-way concern raised by adjacent property owner. Coordinating with barangay officials.
Next steps
Mobilize additional crew to recover 2-day slippage from weather delay.