Livelihood Processing Center – Coron-coron
PRG-2026-164· Coron-coron·Monthly Report
PRG-2026-164 — Monthly Progress Report
MAT-2025-098 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
SubmittedMonthly34d behind
Report Information
- Report code
- PRG-2026-164
- Report type
- Monthly
- Status
- Submitted
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2025-098
- Project title
- Livelihood Processing Center – Coron-coron
- Project type
- Livelihood
- Barangay
- Coron-coron
- Contractor
- Matnog Builders Cooperative
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 48% → 96% (+48%)
- Financial progress
- 46% → 93% (+47%)
- Slippage
- 34 days behind schedule
96%
Issues & Next Steps
- Issues & concerns
- Concrete testing results within specification. Compression strength at 28 days: 4,200 PSI.
- Next steps
- Install drainage outfall and connect to existing municipal system.