Livelihood Processing Center – Coron-coron

PRG-2026-164· Coron-coron·Monthly Report

PRG-2026-164 — Monthly Progress Report

MAT-2025-098 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

SubmittedMonthly34d behind
Physical progress96%
Financial progress93%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+48% physical this period

Report Information

Report code
PRG-2026-164
Report type
Monthly
Status
Submitted
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2025-098
Project title
Livelihood Processing Center – Coron-coron
Project type
Livelihood
Barangay
Coron-coron
Contractor
Matnog Builders Cooperative

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
48% → 96% (+48%)
Financial progress
46% → 93% (+47%)
Slippage
34 days behind schedule
96%

Issues & Next Steps

Issues & concerns
Concrete testing results within specification. Compression strength at 28 days: 4,200 PSI.
Next steps
Install drainage outfall and connect to existing municipal system.