Day Care Center Construction – Caloocan
PRG-2026-173· Caloocan·Monthly Report
PRG-2026-173 — Monthly Progress Report
MAT-2025-103 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026
ReturnedMonthly
Report Information
- Report code
- PRG-2026-173
- Report type
- Monthly
- Status
- Returned
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- Aug 28, 2026
- Last updated
- Sep 15, 2026
Project Information
- Project code
- MAT-2025-103
- Project title
- Day Care Center Construction – Caloocan
- Project type
- Social welfare
- Barangay
- Caloocan
- Contractor
- Matnog Builders Cooperative
Reporter Details
- Submitted by
- Engr. Rafael T. Dizon
- Designation
- Project Engineer
Progress Summary
- Physical progress
- 43% → 86% (+43%)
- Financial progress
- 41% → 82% (+41%)
- Slippage
- On track
86%
Issues & Next Steps
- Issues & concerns
- No significant issues encountered during reporting period. Work proceeding as planned.
- Next steps
- Prepare for pre-final inspection. Complete punch list items.