Level III Water System Expansion – Tabunan
PRG-2026-179· Tabunan·Monthly Report
PRG-2026-179 — Monthly Progress Report
MAT-2025-107 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026
DraftMonthly
Report Information
- Report code
- PRG-2026-179
- Report type
- Monthly
- Status
- Draft
- Period
- Aug 15 – Aug 28, 2026
- Submitted date
- —
- Last updated
- Sep 9, 2026
Project Information
- Project code
- MAT-2025-107
- Project title
- Level III Water System Expansion – Tabunan
- Project type
- Water supply
- Barangay
- Tabunan
- Contractor
- South Luzon Infrastructure Corp.
Reporter Details
- Submitted by
- LGOO Ana P. Santos
- Designation
- Local Government Operations Officer
Progress Summary
- Physical progress
- 31% → 63% (+32%)
- Financial progress
- 34% → 69% (+35%)
- Slippage
- On track
63%
Issues & Next Steps
- Issues & concerns
- Workforce reduced to 60% due to local fiesta. Full crew expected next reporting period.
- Next steps
- Conduct concrete strength test and proceed with second floor slab if passed.