Level III Water System Expansion – Tabunan

PRG-2026-179· Tabunan·Monthly Report

PRG-2026-179 — Monthly Progress Report

MAT-2025-107 · LGOO Ana P. Santos · Aug 15 – Aug 28, 2026

DraftMonthly
Physical progress63%
Financial progress69%
Reporting periodAug 15 – Aug 28, 2026Not yet submitted
Work items4+32% physical this period

Report Information

Report code
PRG-2026-179
Report type
Monthly
Status
Draft
Period
Aug 15 – Aug 28, 2026
Submitted date
—
Last updated
Sep 9, 2026

Project Information

Project code
MAT-2025-107
Project title
Level III Water System Expansion – Tabunan
Project type
Water supply
Barangay
Tabunan
Contractor
South Luzon Infrastructure Corp.

Reporter Details

Submitted by
LGOO Ana P. Santos
Designation
Local Government Operations Officer

Progress Summary

Physical progress
31% → 63% (+32%)
Financial progress
34% → 69% (+35%)
Slippage
On track
63%

Issues & Next Steps

Issues & concerns
Workforce reduced to 60% due to local fiesta. Full crew expected next reporting period.
Next steps
Conduct concrete strength test and proceed with second floor slab if passed.