Drainage Canal Improvement – Sisigon

PRG-2026-188· Sisigon·Monthly Report

PRG-2026-188 — Monthly Progress Report

MAT-2025-112 · Engr. Rafael T. Dizon · Aug 15 – Aug 28, 2026

ArchivedMonthly34d behind
Physical progress53%
Financial progress58%
Reporting periodAug 15 – Aug 28, 2026Submitted Aug 28, 2026
Work items4+27% physical this period

Report Information

Report code
PRG-2026-188
Report type
Monthly
Status
Archived
Period
Aug 15 – Aug 28, 2026
Submitted date
Aug 28, 2026
Last updated
Sep 15, 2026

Project Information

Project code
MAT-2025-112
Project title
Drainage Canal Improvement – Sisigon
Project type
Drainage
Barangay
Sisigon
Contractor
South Luzon Infrastructure Corp.

Reporter Details

Submitted by
Engr. Rafael T. Dizon
Designation
Project Engineer

Progress Summary

Physical progress
26% → 53% (+27%)
Financial progress
29% → 58% (+29%)
Slippage
34 days behind schedule
53%

Issues & Next Steps

Issues & concerns
Concrete testing results within specification. Compression strength at 28 days: 4,200 PSI.
Next steps
Install drainage outfall and connect to existing municipal system.